This page contains information and links relevant to the Single Undulator Test (SUT). For an introduction please read the LCLS Single Undulator Test Plan document.
Link to the current layout of the SUT (SUT_Layout_Rev_04.ppt)
Summary Schedule (Link to current master schedule)
Name |
Duration |
Start_Date |
Finish_Date |
Assembly |
38 days |
Thu 3/16/06 |
Mon 5/8/06 |
Install fixed supports |
5 days |
Thu 3/16/06 |
Wed 3/22/06 |
Install connecting plates |
3 days |
Thu 3/23/06 |
Mon 3/27/06 |
Install Cams |
2 days |
Tue 3/28/06 |
Wed 3/29/06 |
Install girder |
2 days |
Thu 3/30/06 |
Fri 3/31/06 |
Install translation stages |
1 day |
Mon 4/3/06 |
Mon 4/3/06 |
Install undulator |
1 day |
Tue 4/4/06 |
Tue 4/4/06 |
Install measurement hardware |
2 days |
Wed 4/5/06 |
Thu 4/6/06 |
Perform segment replacement testing |
5 days |
Fri 4/7/06 |
Thu 4/13/06 |
Remove measurement hardware |
1 day |
Fri 4/14/06 |
Fri 4/14/06 |
Install Quad |
3 days |
Mon 4/17/06 |
Wed 4/19/06 |
Install and align vacuum support |
3 days |
Thu 4/20/06 |
Mon 4/24/06 |
Install vacuum chamber |
4 days |
Tue 4/25/06 |
Fri 4/28/06 |
Install BPM support |
2 days |
Mon 5/1/06 |
Tue 5/2/06 |
Install BPM |
1 day |
Wed 5/3/06 |
Wed 5/3/06 |
Install BFW support |
2 days |
Thu 5/4/06 |
Fri 5/5/06 |
Install BFW |
1 day |
Mon 5/8/06 |
Mon 5/8/06 |
Install HLS System |
3 days |
Tue 4/25/06 |
Thu 4/27/06 |
Install WPM System |
3 days |
Fri 4/28/06 |
Tue 5/2/06 |
Install mu metal shield |
3 days |
Wed 5/3/06 |
Fri 5/5/06 |
SUT Assembly Complete |
0 days |
Fri 5/5/06 |
Fri 5/5/06 |
Install first Article Undulator |
1 day |
Mon 5/8/06 |
Mon 5/8/06 |